Five procedures. Procedure 1 runs before the others and is the one this unit is built on.
Measurement procedures are in GEN-E Procedures and are not repeated here (GEN-K Quick reference).
Procedure 1 — Select an inspection technique (R4)
Given — a part, and a reason to inspect it. Sought — a method that could actually find what you are looking for.
Method
- Name what you are looking for. A fatigue crack. Corrosion under a lap. A disbond. Wear beyond a limit. "Anything wrong" is not an answer and does not lead to a method.
- Say where it would be. Surface or subsurface. At a hole, a radius, an edge, a bond line.
- Name the material. Ferrous, non-ferrous, composite, porous.
- Choose the method that can see there, in that material (GEN-K Concepts §1).
- Check what the approved data requires. If the manufacturer specifies a method, that governs — your reasoning confirms it rather than replaces it.
- State the method's blind spot and decide whether it matters.
Check — complete this sentence: "If the defect were present, this method would find it, because …" If you cannot, you have chosen a method rather than selected one.
Failure — dye penetrant on a subsurface crack, magnetic particle on aluminum, a tap test on solid laminate. Each returns clean. Each is recorded as an inspection.
Procedure 2 — Perform a visual inspection (S4)
Method
- Establish the scope from approved data — what area, what you are looking for, what the limits are.
- Clean the area. Much of what is found is found while cleaning.
- Arrange lighting, including raking light across the surface.
- Work a pattern — a defined start, a defined route, a defined end.
- Use aided vision: magnifier, mirror, borescope where access requires it.
- Concentrate on stress concentrations: holes, radii, edges, fastener heads, weld toes, changes of section.
- Measure anything you find, against the limit in approved data.
- Record what you inspected, what you found, and the disposition.
Check — can you describe your coverage pattern? If you cannot say where you started and where you finished, you did not cover it — you looked at it.
Failure — inspecting only what is easy to see. Failures concentrate where access is worst, because that is where inspection is least often done.
Procedure 3 — Perform a dye penetrant inspection (S5)
Confirm first that the material is non-porous and the defect would be surface-breaking (Procedure 1).
Method
- Clean thoroughly and dry. Penetrant cannot enter a defect filled with oil, paint or corrosion product. This step decides the result.
- Apply penetrant and observe the dwell time in the kit's instructions. Too short and it has not entered; too long and it dries in place.
- Remove surface penetrant by the specified means — and no more. Over-cleaning pulls penetrant back out of the defect and the indication disappears.
- Apply developer thinly and evenly.
- Observe over time. Indications develop and grow; a bleed-out that widens is a real defect, a spot that appears at once and does not change may be surface contamination.
- Evaluate against the acceptance criteria, and clean the part afterwards.
Check — an inspection that finds nothing on a part you know to be cracked has failed, not passed. Process a known-defective reference specimen alongside the work to confirm the technique and materials are working.
Failure — inadequate pre-cleaning. The commonest cause of a false clean result, and it looks exactly like a good inspection.
Procedure 4 — Perform a tap test (S8)
Confirm first that the structure is thin skin over core, not solid laminate (Procedure 1).
Method
- Use the specified tapper — a coin-sized tap hammer, not a screwdriver handle.
- Establish the sound of good structure by tapping a known-sound area first.
- Tap in a grid pattern, consistent force, moving systematically.
- Listen for a change — a dull, flat or dead response against the sharp response of bonded structure.
- Mark the boundary of any suspect area and map its extent.
- Confirm by another method where the approved data requires it.
Check — step 2 is the check. Without a known-good reference, "dull" has no meaning. If you have not established the good sound, you cannot recognize the bad one.
Failure — tapping too hard, which damages the structure, or too inconsistently, which makes every response sound different.
Procedure 5 — Inspect for AD compliance (S6)
Method
- Establish which ADs apply (GEN-I Procedures Procedure 3).
- Read what the AD requires you to inspect, by what method, at what interval, to what criteria.
- Perform it — by the specified method. An AD that calls for eddy current is not satisfied by a visual inspection.
- Record compliance: the AD number and revision, the method, the finding, the date and time in service, and the next due point if recurring (GEN-I Procedures Procedure 6).
Check — read your record back against the AD's compliance paragraph. Every requirement it states should be answered in your entry.
Failure — substituting a method. If the AD specifies a technique, an alternative needs an AMOC, not a judgment.
The checks, collected
| Procedure | The check |
|---|---|
| Technique selection | "If it were present, this method would find it, because …" |
| Visual | Describe your coverage pattern |
| Dye penetrant | Process a known-defective reference alongside |
| Tap test | Establish the good sound before listening for the bad |
| AD compliance | Read your entry back against the compliance paragraph |
Four of the five checks are about proving the method could have found it. That is what separates an inspection from a look, and it is why GEN-K Concepts §6 treats a clean result as a claim rather than an observation.
License
CC BY-SA 4.0 (Licensing).