Eight procedures. Guided first attempts are in AF-K Hands-on.
Measurement procedures are in GEN-A Procedures and are not repeated here.
Procedure 0 — De-energize, and know what is near you (R1–R4)
- Identify the circuit from the wiring diagram.
- De-energize: pull the breaker, disconnect the battery where the work requires it, disconnect external power.
- Confirm dead with a meter, at the point you will be working.
- Look at what else is in the bay.
R4— the hazard is damaging a conductor you were not thinking about (AF-K Concepts §3). - Protect adjacent looms before drilling, cutting or levering anything.
Check — confirm dead at the point of work, not at the panel. Two circuits can share a bay and only one of them is the one you pulled.
Procedure 1 — Determine the electrical load, and size the wire from it (S9, R6)
S9 is the load; R6 is the wire. The procedure was previously titled for the wire size
alone, which named it after R6's output rather than after the element it assesses.
- Establish the load current. Sum the connected loads on the circuit or bus, and establish for each whether it is continuous or intermittent — only continuous load counts against the continuous-duty limit. Compare the total against the generator or bus rating and against the percentage of rating the manual allows continuously; the margin that remains is what any added equipment has to fit inside.
- Measure the run length, out and back.
- Find the allowable voltage drop for that system from the manual or AC 43.13-1B.
- Select from the chart, using both current capacity and voltage drop — take the larger size the two give (AF-K Concepts §4).
- Adjust for bundle size and ambient temperature, which reduce capacity.
- Size the protective device to protect the wire.
Check — compute the voltage drop for the size you chose and compare against the limit. Sizing on current alone is the standard error, and on a long run it fails the drop check.
Failure — sizing the breaker to the load. The breaker exists to stop the wire overheating; if it is larger than the wire can stand, the wire is the fuse.
Procedure 2 — Strip and terminate (S2)
- Select the correct terminal for wire gauge and stud size.
- Strip to the length the terminal requires — no more. Exposed conductor beyond the barrel is a short waiting to happen.
- Do not nick the strands. A nicked conductor fails at the nick, later, from vibration.
- Crimp with the correct tool and the correct die, fully cycled.
- Inspect: insulation not in the conductor barrel, conductor visible at the inspection window where the terminal has one, no strands outside the barrel.
- Pull-test to the specified value where required.
Check — give it a firm pull. A correct crimp does not move. This takes a second and it catches the crimp made with the wrong die.
Failure — a crimp made with pliers or the wrong die. It holds on the bench and releases under vibration.
Procedure 3 — Splice (S2)
- Confirm a splice is permitted here — the manual and AC 43.13-1B limit how many splices a run may have and where they may be.
- Stagger splices in a bundle so they do not form a bulge.
- Use the approved splice for the gauge, crimped with the correct tool.
- Insulate and seal per the approved method.
- Support the splice — it must not carry load or sit at a flexing point.
Check — a splice must be supported and staggered. A bundle with several splices at the same point is stiff, bulky and chafes.
Procedure 4 — Assemble a connector (S3)
- Identify the connector and its contact type — pin, socket, size, and whether crimp or solder.
- Check the wiring diagram for pin assignment, and mark the wires before starting.
- Crimp contacts with the correct tool and positioner.
- Insert contacts with the insertion tool until they click home, and confirm with the removal tool's resistance or a gentle pull.
- Fit sealing plugs in unused cavities — an unplugged cavity admits moisture.
- Assemble the backshell, supporting and clamping the cable so strain is taken by the shell, not the contacts.
Check — tug each wire gently at the back of the connector. A contact that has not latched comes back out, and it will do so in service if it does not do so now.
Failure — a contact not fully seated. It works on test and backs out under vibration, producing an intermittent that is very hard to find.
Procedure 5 — Solder, where it is called for (S5, R8, R9)
First confirm soldering is what the approved data calls for (AF-K Concepts §2).
- Clean the conductor and the joint.
- Use the specified solder and flux — and never acid flux on electrical work; it corrodes the joint from the inside.
- Heat the work, not the solder. Solder should melt on the joint, not be dripped onto it.
- Use just enough solder to wet the joint. Excess wicks up the strands and extends the rigid section.
- Do not move the joint while it cools. A disturbed joint looks dull and grainy and is weak.
- Clean off flux residue.
- Support the wire so the joint is not a flex point — this is the whole point of
R8.
Check — the joint should be shiny and smooth, with the wire outline visible through it. Dull, grainy or blobby means it was disturbed, too cold, or over-soldered.
Failure — an unsupported solder joint at a flex point. It is a designed-in fatigue failure.
Procedure 6 — Route and secure a bundle (S8, R5)
- Follow the routing the drawing specifies, and the existing route where you are replacing.
- Clamp at the specified intervals with the specified clamps — correct size, cushioned, not over-tightened.
- Maintain separation: from control cables, moving parts, hot sections, and fluid lines. Never below a fluid line (AF-K Concepts §6).
- Respect bend radius, and leave service loops at connectors.
- Provide drip loops so fluid runs away from connectors.
- Check for chafe points through full travel of anything that moves.
Check — move everything that moves, through full travel, and watch the bundle. Controls, gear, flaps, doors. Chafe is found this way and not by looking at a static aircraft.
Procedure 7 — Install a bonding jumper (S10)
- Prepare both surfaces: remove paint, anodizing and corrosion products to bare, clean metal at the contact area only.
- Fit the jumper with the specified hardware, metal to metal at the contact faces.
- Torque per the manual.
- Measure the resistance across the bond and compare against the manufacturer's limit.
- Restore corrosion protection around the joint without insulating the contact faces (GEN-G Concepts §3).
Check — measure it. Bonding is the one thing in this unit with an objective numerical pass criterion, and a bond that looks fine and reads high is doing nothing.
Failure — bonding through paint or anodizing. It looks like a bond and is an insulator.
The checks, collected
| Procedure | The check |
|---|---|
| De-energize | Confirm dead at the point of work |
| Wire sizing | Compute the voltage drop for the size you chose |
| Terminate | Give it a firm pull |
| Splice | Supported and staggered |
| Connector | Tug each wire at the back |
| Solder | Shiny and smooth, wire outline visible |
| Routing | Move everything that moves, and watch |
| Bonding | Measure the resistance |
License
CC BY-SA 4.0 (Licensing).